Week Two started with us a few days ahead of the planned schedule. Painting the walls with Farrow & Ball Pavilion Grey No242 began to give a better feel for the shop as a space. The interior paintwork has a fiddly detailed door and window structure, proving quite a job and a half. Endeavouring to cover its dark green paintwork required two coats of undercoat before glossing could even commence. We laid laminate flooring in and under the window. Lighting strips were installed for us. All bar one of our orders placed in Harrogate arrived and they all look as good as we remembered. I made a cover to hide some rather ugly meters which is now referred to as 'The Monolith'. Its been hard graft after hard graft, with us sleep deprived but indominatable. We finished the week with a day of clearing up and cleaning as next week the shop fittings start arriving. Woo woo!
|